Evidences from KPO website shows appreciation for Bonatti - JSC Montazhspetsstroy operations.
Companies were awarded by KPO the contract for the execution of the 4th Re-Injection Compressor Project: a compressor island with a three stage centrifugal driven compressor. Since the beginning of the project, Bonatti started to train local personnel to enhance HSE skills, efficiency and productivity .
With this aim, the company mobilized all the needed equipment including a semi-automatic welding machine, Submerged Arc Welding (SAW), for the welding of F22 piping (80 mm thick) at its Base at Tungush (Burlin District) and started an intensive training process for the qualification of local welders including the SAW machine operators.
PROJECT HIGHLIGHTS
• Fast-track project execution
• Installation: one GE MS5002D gas turbine
• Scope of work: maintain levels of production
• Challenge: train personnel for the welding of F22 high-thick piping with a wall thickness of 80 mm, 16 inches diameter and pressure up to 605 bar
This initiative is an example of successful cooperation with Kazakhstani skilled workers with the efforts and commitment to develop local content in the country.